Air Quality Bureau
Power Generation Projects in New Mexico
| Company / Facility | NSR & TV Permit File No. | Location | Unit(s) or Type | Size | Status | Company Contact |
| PNM / Luna Energy Facility | PSD-2450-M2 TV P209R1 |
Deming, Luna County |
2 - Natural Gas Turbines | 618 MW | PSD-2450-M2, ruled incomplete 7/8/10 P209R1, Ruled Complete 10/2/12 |
Mark Williams Mark.Williams@pnmresources.com |
PNM / Afton Generating Station |
PSD-2466-M3 TV P211-R1 |
Las Cruces, Dona Ana County | 1 -Natural Gas turbine | 280 MW | PSD-2466-M3 Issued 12/6/10 P211-R1M2 Issued 3/10/12 |
Robin Delapp Robin.DeLapp@pnmresources.com |
| PNM / Lordsburg Generating Station | 2613 TV P214-R1 |
Lordsburg, Hidalgo County | 2 - Natural Gas Turbines | 82.2 MW | 2613 Issued 1/18/02 P214-R1 Issued 6/7/10 |
Mark Williams Mark.Williams@pnmresources.com |
| PNM / San Juan Generating Station | 0063-M8 TV P062-R2M2 |
Waterflow, San Juan County | 4 - Coal Fired Boilers 1 - Steam Turbine |
1799 MW | 0063-M8, Issued 8/31/12 P062-R2M2 Ruled Complete 6/14/12 |
Mark Williams Mark.Williams@pnmresources.com |
| Tri-State / Pyramid Generating Station | 2550-R2 TV P217-R1 |
Lordsburg, Hidalgo County | 4 - Natural Gas turbines | 180 MW | 2550-R2 Issued 7/25/02 P217-R1 Issued 4/14/11 |
Sherri Livengood slivengood@tristategt.org |
Tri-State / Prewitt Escalante Generating Station |
PSD-285-M3 TV P012-R2 |
Prewitt, McKinley County | 1 - Natural Gas Boiler | 260 MW | PSD-285-M3 Issued 5/10/93 P012-R2 Issued 8/8/11 |
Dan Salgado dsalgado@Tristategt.org |
| Freeport McMoRan / Tyrone Mine | 2448-R7 TV P147R1 |
Tyrone, Grant County | 10 - Natural Gas/Diesel duel fuel IC engines (Standby) |
20 MW | 2448R7 Issued 4/14/12 P147R1 Issued 10/25/10 |
Edward Horst 575-912-5759 edward_horst@fmi.com |
| Freeport McMoRan / Chino Mine | 0298-M6 TV P066-R2 |
Vanadium, Grant County | 1 - Natural Gas Turbine (Standby) |
65.5 MW | 0298-M6 Issued 9/14/12 P066-R2 Ruled complete 3/5/12 |
Kervin Cook 575-912-5215 Kevin_Cook@fmi.com |
| Valencia Power LLC / Valencia Power Plant | 2620-M1 TV P220 |
Belen, Valencia County | 2 - Natural Gas Turbines | 319 MW | 2620-M1 Issued 10/4/10 P220 Issued 1/3/11 |
Randy Fox 303-999-5928 FoxR@southwestgen.com |
| EL Paso Electric Co/ Rio Grande Generating Station | 1554-M1 TV P127-R2 |
Sunland Park, Dona Ana County | 3 - Natural Gas Boilers 1 - Natural Gas Turbine |
349.8 MW | 1554-M1 Issued 6/9/11 P127-R2 issued 10/12/11 |
Luis Perez 915-543-4166 luis.perez@epelectric.com |
| Raton Public Service / Raton Generation Project | 2761 | Raton, Colfax County | 1 - Natural Gas IC engine | 7.3 MW | Issued 12/04/02 |
Glenn Fisher 505-445-9861 glenn.fisher@netscape.com |
| City of Farmington / Bluffview Power Plant | 2831-M1 TV P228R1 |
Farmington, San Juan County | 1 - Natural Gas Turbine | 60 MW | 2831-M1 Issued 1/14/04 P228R1 Ruled complete 12/29/11 |
Mike Sims 505-599-8342 msims@fmtn.org |
| Tyson Prepared Foods / Prepared Foods Distributed Generation System | 2836R1 | Santa Teresa, Dona Ana County | 2 - Diesel IC Engines (Standby) |
2 MW | Issued 12/12/03 |
John Watley 575-589-7418 |
| North East New Mexico Biomass | 2939 | Raton, Colfax County | Wood Biomass Boiler | 35 MW | Issued 3/15/04 (not built) |
Jack Maddox 505-332-3279 maddoxengr@aol.com |
| Lea County Electric Coop /Lea County Electric Cooperative Power Plant | 4224 | Lovington, Lea County | 6- Natural Gas IC Engines | 47 MW | Issued 12/13/2010 |
Gary Hurse 575-396-3631 ghurse@lcecnet.com |
| Los Alamos National Security LLC / Los Alamos National Laboratory | 2195B-M2 P100R1M1 |
Los Alamos, Los Alamos County | 1 - Natural Gas Turbine | 24 MW | 2195B-M2 Issued 11/1/11 P100R1M1 Issued 6/15/12 |
Bill Blankenship bblankenship@lanl.gov |
| Lea Powers Partners LLC / Hobbs Generating Station | PSD3449M1 TV P244M3 |
Hobbs, Lea County | 2 - Natural Gas Turbines | 600 MW | PSD3449M1 Issued 9/23/11 P244M3 Ruled Complete 8/23/12 |
Roger Schnabel 575-397-6706 rshnabel@camstex.com |
| Estancia Basin / Biomass Power Generation Plant | 3434 | Estancia, Torrance County | Biomass Boiler | 35 MW | Issued 10/16/07 (not built) |
Jack Maddox 505-332-3279 maddoxengr@aol.com |
| SW Public Service Co / Cunningham Station | PSD-622-M4 TV P080-R2M1 |
Hobbs, Lea County | 2 -Natural Gas Turbines 2 - Natural Gas Boilers |
560 MW | PSD-622-M4 Issued 5/23/12 P080-R2M1 Ruled complete 6/28/12 |
Kevin Worley 806-378-2121 Kevin.L.Worley@xcelenergy.com |
| SW Public Service Co / Quay County Generating Plant | 4561 | Tucumcari, Quay County | 1 - Diesel Turbine | 23 MW | 4561 Issued 1/25/12 |
Gale Henslee 806-378-2197 gale.henslee@xcelenergy.com |
| City of Farmington / Animas Power Plant | 1061M1 | Farmington, San Juan County | 1 - Natural Gas Turbine | 18.6 MW | 1061M1 Issued 8/29/12 | Mike Sims 505-599-8342 msims@fmtn.org |
If you have questions about this information, please contact ned.jerabek@state.nm.us of the New Mexico Air Quality Bureau